Howard University > Net 3 > - ISAS Technology Center (New Core MDF)
The placement of the new 130kVa Liebert UPS consisted of the removal of a old 80 kVa UPS. The project was started by the design of a cutover procedure to allow a smooth cutover between the old and new UPS. The construction began with electrical Taps being bridged into existing electrical circuits. Once all Taps where place the 130kVa Liebert UPS was installed. The cutover consisted of the throwing all electrical circuits from the 80kVa UPS to the 130kVa Liebert UPS.
|